The appellant has sought List of the independent power producers in Pakistan and Certified copies of all agreements signed with independent power producers so far.
He also sought copy of the inquiry committee report that was formed by the Imran Khan led government to investigate independent power producers (IPPs) in 2019/2020.
This Commission allowed the appeal and directed the Deputy Secretary (Coord), Minsitry of Energy (Power Division) and Managing Director, Central Power Purchasing Agency to provide complete information to the Appellant, at the earliest but not later than 7 working days of the receipt of this Order.